The following are the high level key timings for the V13.00.00 Schema Release. All dates are indicative and subject to change via on-going engagement with ESBN, NIE Networks and subsequent approval at ReMCoSG.
TOPIC | ELEMENT | INDICATIVE UPDATE DATES(TBC) |
---|---|---|
Implementation Details (ROI Only) | RMP Extranet Screenshots Sample MMs Downloadable Meter Points Files MCR1135 Webservice MetaData |
End of Q3 2020 |
Market Assurance (ROI) | Market Participant Self Assessments (PQ) | 1st Engagement Q3 2019 2nd Engagement Q2 2020 |
Cutover & Contingency Planning | Cutover/Go-Live Period | End of Q3 2020 |
V13.00.00 Schema- Formal Publication |
Schema for IPT Purposes (NI & ROI) |
End of Q3 2020 |
Market Assurance (Co-Ordinated) | IPT Window (NI & ROI) | Q3/Q4 2020 |
Market Assurance (ROI) | Market Assurance Approach |
Q3 2019 |
Sharing of DRAFT V13.00.00 Schema | ESBN & NIE Networks will confirm approach & timelines | Q3 2019 |
Market Design | MCR Re Versioning High Level Plan | Q3 2019 |