MCR 1137 introduces a change to the contents of the Downloadable Meter Points Data file whereby only billable meters will be shown.
At present non-billable meters are shown as well as billable meters. ESB Networks assessed the changes required to the Central Market Systems to support this MCR as of low complexity.
The following table will display a status of the MCR delivery process.
Event | Date | Status |
---|---|---|
Participant Questionnaire issued | 7th March 2014 | Complete |
Participant Questionnaire returned | 14th March 2014 | Complete |
ESBN complete development | TBD | |
Requestors of MCR to validate file contents | TBD | |
Gemserv Report to CER | 19th March 2014 | Complete |
CER Go/No-Go Decision | 25th March 2014 | Complete |
Cut Over | 10th April 2014 |