Gemserv have issued Assurance strategy for the Non Schema Release 2015. This can be accessed here.
The following table displays all relevant Assurance dates for both MCRs.
MCR1136 | MCR151 | |
---|---|---|
Participant Questionnaire issued | 21 Aug 2015 | 21 Aug 2015 |
Participant Questionnaire returned | 11 Sept 2015 | 11 Sept 2015 |
Site visit to ESB Networks | 12 Sept – 2 Oct 2015 | 12 Sept – 2 Oct 2015 |
Inter-Participant Testing Window | N/A | N/A |
Gemserv report to CER | 16 Oct 2015 | 16 Oct 2015 |
CER Go / No-Go decision | 30 Oct 2015 | 30 Oct 2015 |
Cut-Over | 20-22 Nov 2015 | 20-22 Nov 2015 |
The assurance applicable to the different Market Participant types are displayed in the following table.
Participant type |
ESB Networks | Supplier | Small Supplier |
Self-Supplier | TSO (EirGrid) |
---|---|---|---|---|---|
Self Assessment |
MCR1136 MCR1151 |
MCR1151 | MCR1151 | N/A | N/A |
Formal Assessment |
MCR1136 MCR1151 |
MCR1151 | MCR1151 (Volunteers Only) |
N/A | N/A |
IPT | N/A | N/A | N/A | N/A | N/A |