MCR 1107 – New ‘Connection Card Required’ code on 102P

This request proposes the introduction of a new ‘Provisional Acceptance Completion Requirement Code’ code for the 102P market message to notify the Supplier that a Connection Card is required before the meter works requested on the 010 (CoS) can be completed.

This 102P will return this code when

– an 010 (CoS) is submitted with Meter Works included, and

– the Meter Works involve a change to an MCC which includes heating, and

– the premise does not currently have an MCC which includes heat.

NIE need to know the additional Heating Load that is required at the premise and the Connection Card will provide this information.

The CoS meter works will not proceed until NIE have received a valid Connection Card from the Customer.