WP 0014 Distribution Connected Non Participant Generator Export Arrangements Working Practice was baselined at version 6.0 as detailed within MCR 125 v1.1 as part of the suite of changes to the Retail
Market Design to satisfy new requirements of SEM implementation.
WP 0014 Distribution Connected Non Participant Generator Export Arrangements is to be updated to
reflect the following:
It is a Regulatory requirement that in the new manual registration process for Non-Participant
Generation, a Supplier must show that they have historic demand that has been (in all Trading Periods)
1.5 times greater than the maximum contracted output of all out-of-market generation contracted to that Supplier Unit.