The following changes are required to MPD5 New NQH Metered to cater for proposed new
arrangements for QH Eligibility
MPD5 New NQH Metered Connection
All new connections at LV (excluding embedded generators) will be set up as NQH(currently LV new
connections at 200KVA or higher are set up as QH).