DR 0051 – Changes to MPD 12 – Meter problems and damage

There are some minor changes required to the MPD for meter problems and damage. The MPD should be updated to include some additional detail on how ESB Networks will handle the process for meter problems and damage. The order of…

Read More

MCR 0043 – Minor Changes arising to Market Messages arising from testing

A number of minor changes are required to the market messages arising from errors found in testing. The changes required are: Market Message 110 CoS read arrangement is a mandatory field. As this field is optional on message 010 (i.e….

Read More

MCR 0042 – Clarifications to MPD 3

A number of changes are required to the CoS objection & cancellation process. Cancellation MPD The process flow following the decision diamond after Step 5 (CoS Incomplete or open objection) needs to be made more explicit and the text associated…

Read More

MCR 0041 – Changes to MPD 12 – Meter Problems and damage

There are some minor changes required to the MPD for meter problems and damage. The MPD should be updated to include some additional detail on how ESB Networks will handle the process for meter problems and damage. The order of…

Read More

MCR 0040 – Clarifications to MPDs arising from supplier clarifications

MPD 1 Clarification required to wording around Page 10 (‘Where a customer read is requested then…..”) To “”Where a customer reading is requested but not provided & validated with the registration request then…if no valid reading becomes available in the…

Read More

MCR 0039 – Optionality of Supplier ID on 111 field

Supplier ID is currently listed as a mandatory field on Market Message 111 (Registration Cancellation). The optionality of this field should be changed to D – Mandatory in the case of CoS cancellation. Click here to open the document.

Read More

MCR 0038 – Changes to segments on 331 and 332

The Removed, New and Retained Meters Segment on the 331, 332 and 332W messages need to be removed to allow the Market Messages DB and Message Guides to be brought in line with the XML Schema. The Meter ID segment…

Read More

MCR 0037 – Addition of Irish County Codes and UK country code

Codes. Legacy addresses with counties in Irish will be migrated with the existing Irish counties, The agreed market data codes for ‘Ireland – County’ will need to be updated to include the additional Irish codes. Click here to open the…

Read More

MCR 0036 – Changes to Codes

The codes for withdrawal reason need to be changed from 01 Incorrect Estimation 02 Incorrect Meter Reading 03 Erroneous Change of Supplier 04 Disputed CoS Meter Reading 05 Incorrect Rate Click her to view the document.

Read More

MCR 0035 – Registration as implicit request for energisation

New process for registration of sites which are currently de-energised is that the receipt of the validated registration request is an automatic request for energisation. This is not how the process currently works and should not change. The current process…

Read More

MCR 0032 – Clarify relationship between 013 and 114 messages on MPD 24

A supplier may request multiple changes to customer details for the same MPRN on a single instance of message 013. It is possible that some changes may be confirmed immediately while others may require investigation by DSO prior to confirmation….

Read More

MCR 0031 – Updates to market messages 101 and 101P to include load profile

Load Profile is required to be added to market message 101 and 101P at the MPRN level. Click here to view the document.

Read More

MCR 0030 – Updates to market message implementation guides

A number of changes are required to the Market Message Implementation guides to ensure clarity and accuracy. 1. Common Data Segments: Treatment of Technical Contact details is incorrect. This comprises a Contact name (field), Technical Contact Details (Segment) and Technical…

Read More

MCR 0029 – Updates to metered MPDs to include unmetered processes

The following changes are required to existing metered MPDs to support the single site unmetered market: • MPD 9: De-energisation: Market Message 700 will be sent to confirm de-energisation for unmetered sites rather than Market Message 106D • MPD 10:…

Read More

DR 0052 – Change to DUoS Detailed Flat file

The due date of the aggregated invoice should be included in the header of the detailed flat file Click here to read the document.